Skip to Main Content
Midtown ATL

Under Construction

Monthly Projects Update: October 8, 2024

Each month, we provide a construction update on our current Capital Improvement projects. See what's happening as we give you more to love about Midtown.

Projects Currently Under Construction

Click the project name below to learn more!

1.  Juniper Complete Street

Construction mobilized within the public right-of-way in May 2023 and completed the majority of new curbs and sidewalks, ADA ramps and improvements on the east side of Juniper Street by February 2024. In March 2024, work shifted to portions of the west side of Juniper Street. The majority of streetlights have been installed and energized. Erosion control and traffic control maintenance is ongoing. Project contractors install daily lane closures and pedestrian detours as needed to enable safe work. In the near future, Midtown can expect to see new trees planted, stormwater planters, and other landscaping installed. New traffic signal poles and mast arms will go in this fall, as well as roadway pavement repair and resurfacing, and bike lane barriers in the coming months.

2. 5th Street Complete Street

Street and sidewalk conditions will be improved as bike lanes are upgraded, sidewalk and curbing is replaced, ADA ramps are installed, and pedestrian lights are added for safety.

3. 15th Street Extension

Construction of a new multi-modal street connection to extend 15th Street from its current end point at West Peachtree Street two blocks west to Williams Street.

4. Spring Street Bicycle and Pedestrian Improvements Project

The Spring Street Improvements Project proposes to repurpose one southbound lane on Spring Street (US-19/SR-9) between Peachtree Road and 17th Street to accommodate wider sidewalks, ADA upgrades, street trees, pedestrian lighting, and bicycle facilities. 

5. 10th Street Bridge

Midtown Alliance, in partnership with the City of Atlanta Department of Transportation TSPLOST Program, is designing multi-modal enhancements for the 10th Street Bridge spanning the Downtown Connector. Improvements include the creation of a protected two-way bikeway on 10th Street to link up the planned 10th Street multi-use path west of the Connector; a protected two-way bikeway on Williams Street to connect to planned bike facilities on Peachtree Place to the south and 12th Street to the north; enhanced and upgraded sidewalks and crosswalks; gateway features and lighting. Traffic operational improvements to manage traffic flow and address multi-modal conflicts will be implemented. Vehicular improvements include repaving, refreshed lane markings, new lane assignments, and improved signage. New landscaping is also planned, including new tree plantings between Williams Street and the east side of the Connector.

6.  Midtown Art Walk

Phase 1 substantial completion occurred in December 2023. Recently, a new mural and pavement markings went in at 10th Street crosswalk and 11th Street intersection. The City’s major water main break at West Peachtree Street and 11th Street in late May required emergency repair work in the intersection of Peachtree Walk and 11th Street.  The City plans to return to the site to restore the materials in-kind to the state of Art Walk improvements prior to the incident.

7. Sidewalk Improvements (Annual Program)

Pictured below are two of the locations repaired by our construction forces in 2023.  Crews replaced sidewalks and installed ADA-compliant driveway aprons on the north side of 4th Street between Peachtree St and Juniper St.  Damaged sidewalk on the north side of 8th Street just west of Juniper St was replaced, as well as damaged ADA ramps, granite curb and adjacent paver furniture zones on the north side of the 8th St and Peachtree St intersection.  Three new ADA-compliant driveway aprons were constructed on 3rd St between Peachtree St and Cypress St, and on North Avenue between Peachtree St and West Peachtree St.  Other minor hardscape improvements, including grinding sidewalk trip hazards and tree well expansions were made at various locations throughout the District.

The program will continue into 2024, to help maintain and improve pedestrian mobility in Midtown.

Next Up for Construction

Midtown Alliance received construction bids for the 10th Street Bridge project on December 14, 2023. The contract was awarded to F.S. Scarbrough on June 6, 2024, and Notice to Proceed was issued on October 1, 2024.  Active construction will be underway in the coming weeks.

Midtown Alliance also received construction bids for the Spring Street US 19 project on February 29, 2024. The contract was awarded to Hasbun Construction on August 26, 2024.  Notice to Proceed date is October 7, 2024.  Active construction will be underway in the coming weeks.

On the Design Boards

Visit this page to learn more about parks & plazas in the works, enhancements & activation underway, and six more major capital projects in the Design or Procurement phases that are projected to be under construction within one-to-two years.


Our ongoing projects help keep Midtown safe, improve accessibility, and enhance our livability. Contact us with questions or feedback on these projects and construction updates.